某建筑物基础平面图及详图如图2-4( a)、(b)所示,地面做法:20厚1:2.5的水泥砂浆,100厚C10的素混凝土垫层,素土夯实。基础为M5.0的水泥砂浆砌筑标准粘土砖。试求垫层工程量。
图2-4c基础详图
解:①C10的素混凝土地面垫层工程量:
V垫层=( S净- S扣)×δ
=[(3.6×5-0.24×2)×(9-0.24)-0.3 × 0.3 ×3]×0.1
=15.32m3
套定额:2-1-13
②独立基础C10素混凝土垫层工程量:
V垫层= ab×δ×n
=1.3×1.3×0.1×3=0.51 m3
套定额:2-1-13
注意:垫层定额按地面垫层编制,独立基础垫层套定额时人工、机械要分别乘以系数1.10.
③条形基础3:7灰土垫层工程量:
V垫层= V外墙垫+V内墙垫
= S断×L中+ S断×L基底净长
=1.2×0.3×[(9+3.6×5)×2+0.24×3]+ 1.2×0.3×(9-1.2)
=22.51 m3
套定额:2-1-1
注意:条形基础垫层套定额时人工、机械要分别乘以系数1.05.
, CopyImageFlag=null, Format=null, SiteID=1, CatalogID=788, CatalogInnerCode=000020000002000001, TopCatalog=000020, BranchInnerCode=0001, ContentTypeID=Article, Title=复习指导:垫层的内容和计算(二), SubTitle=, ShortTitle=, TitleStyle=null, ShortTitleStyle=null, SourceTitle=, Author=panzhiqiang, Editor=null, Summary=, LinkFlag=N, RedirectURL=null, StaticFileName=/html/2008/12/pa262837445871218002231711.shtml, Status=30, TopFlag=0, TopDate=null, TemplateFlag=N, Template=null, OrderFlag=122947518000000, ReferName=null, ReferURL=null, Keyword=复习指导,垫层,计算, RelativeContent=null, RecommendBlock=null, CopyType=0, CopyID=0, HitCount=0, StickTime=0, PublishFlag=Y, Priority=1, IsLock=null, LockUser=null, PublishDate=2008-12-17 08:53:00.0, DownlineDate=null, ArchiveDate=null, LogoFile=null, Tag=null, Source=, SourceURL=null, Weight=0, ClusterSource=null, ClusterTarget=null, ContributeFlag=null, ContributeUID=0, ConfigProps=NextContent= CKECommentFlag=N PrevContent= Staticize= CommentEnable= CommentEndTime= CommentStartTime= ContentWorkflowInstanceID= , Prop1=PM257094, Prop2=0, Prop3=null, Prop4=null, AddUser=panzhiqiang, AddTime=2008-12-17 08:53:00.0, ModifyUser=, ModifyTime=null, NextContent=, OldPublishFolder=, PrevContent=, Staticize=Y, CommonContentDimCatalogIDSet=null, ContentWorkflowInstanceID=0, CommentEnable=Y, CommentEndTime=, CommentStartTime=, HasBadword=, Name=复习指导:垫层的内容和计算(二), Link=/html/2008/12/pa262837445871218002231711.shtml, ContentPageSize=1, Content=某建筑物基础平面图及详图如图2-4( a)、(b)所示,地面做法:20厚1:2.5的水泥砂浆,100厚C10的素混凝土垫层,素土夯实。基础为M5.0的水泥砂浆砌筑标准粘土砖。试求垫层工程量。
图2-4c基础详图
解:①C10的素混凝土地面垫层工程量:
V垫层=( S净- S扣)×δ
=[(3.6×5-0.24×2)×(9-0.24)-0.3 × 0.3 ×3]×0.1
=15.32m3
套定额:2-1-13
②独立基础C10素混凝土垫层工程量:
V垫层= ab×δ×n
=1.3×1.3×0.1×3=0.51 m3
套定额:2-1-13
注意:垫层定额按地面垫层编制,独立基础垫层套定额时人工、机械要分别乘以系数1.10.
③条形基础3:7灰土垫层工程量:
V垫层= V外墙垫+V内墙垫
= S断×L中+ S断×L基底净长
=1.2×0.3×[(9+3.6×5)×2+0.24×3]+ 1.2×0.3×(9-1.2)
=22.51 m3
套定额:2-1-1
注意:条形基础垫层套定额时人工、机械要分别乘以系数1.05.
}