PM业绩管理练习题及答案

来源: 正保会计网校 编辑:小编 2020/07/09 15:03:06 字体:
1、Alex Co makes specialist computer equipment for the space exploration industry. It recently introduced
a new product, the electroscope. This has to be assembled by hand and the process is very labour
intensive.
A budget was set for the product of 50 hours per unit, based on the time taken to make the first unit.
The first unit was produced in November Actual output and productive labour hours used for the first
six months were as follows:

The management accountant was surprised that the actual production time was below the flexed budget
every month after November. He realised that he had not taken into account the learning curve when he
set the budget.
Required:
(a) Estimate the learning rate for the period. (5 marks)
(b) Determine when the steady state was reached. (5 marks)
【正确答案】 


推荐阅读:

1、ACCA 2020年7月考试时间安排

2、考完ACCA可以获得哪些证书?

3、成为ACCA会员可以享受哪些福利?

4、会计ACCA的就业前景好不好?

免费试听

  • Jessie《FR 财务报告》

    Jessie主讲:《FR 财务报告》免费听

  • 张宏远《MA 管理会计》

    张宏远主讲:《MA 管理会计》免费听

  • 何 文《SBL 战略商业领袖》

    何 文主讲:《SBL 战略商业领袖》免费听

限时免费资料

  • 近10年A考汇总

    历年样卷

  • 最新官方考试大纲

    考试大纲

  • 各科目专业词汇表

    词汇表

  • ACCA考试报考指南

    报考指南

  • ACCA考官文章分享

    考官文章

  • 往年考前串讲直播

    思维导图

回到顶部
折叠
网站地图

Copyright © 2000 - www.chinaacc.com All Rights Reserved. 北京正保会计科技有限公司 版权所有

京B2-20200959 京ICP备20012371号-7 出版物经营许可证 京公网安备 11010802044457号